Module 2: Emergency Planning Notification
 
Return
 
Steps 7 and 8
     
  
 
  
    Using the Optional Aggregation Worksheet A
(continued)
   
     
  
 
  
     
   
Step 9
 
Is the "Weight for 302 " (line K) greater than or equal to the TPQ (line D) for any of the EHSs present at the facility?
Yes
arrow
 
Go to Step 11, "'One-Time Reporting Requirements."
note  
     
    No
arrow
       
     
   
Step 10
       
     
No Emergency Planning Notification is required at this time. If a situation at the facility changes, (i.e., new chemicals added, designation made by the Governor, etc. . .) notification may be required at that time.
   
     
    Continue
 
Module 2, Steps 11 - 14
   
 
Go To: Module 2 Index or EPCRA's Main Index or EPCRA Table of Contents